Project Overview

This 190,000 square foot stainless steel seamless pipe manufacturing plant consists of a 58,800 square foot Hot Mill area, 109,200 square foot Cold Mill area and 22,000 square feet of ancillary areas. The facility is conventional framing with a TPO roof system and tilt-up concrete walls with R-20 insulated wall panels above. The plant also includes a thirty-two foot deep Vertical Press foundation, Horizontal Press, Extruder foundations, furnace foundations and seven overhead bridge cranes. This facility covers all facets of pipe production from billet to finished pipe ready to ship to customers.

Client

Tunica County, Mississippi

Architect

Allen and Hoshall, Memphis, Tennessee

Project Duration

11 Months

Project Size

  • Manufacturing Plant: 190,000 SF Total
  • Hot Mill Area: 58,800 SF
  • Cold Mill Area: 109,200 SF
  • Ancillary Areas: 22,000 SF

Components

  • Conventional Framing
  • TPO Roof System
  • Tilt-up Concrete Wainscot with R-20 Insulated Wall Panels above
  • 32’ Deep Vertical Press foundation
  • Horizontal Press
  • Extruder foundations
  • Furnace foundations
  • Final Stage Pipe Finish
  • (7) Overhead Bridge Cranes

More Projects

JESCO commercial construction company

RSA Judicial Office Building

This new office building is a twelve-story, 400,000 square foot facility. The building encapsulates the historic Alabama Supreme Court Building. The structure

JESCO industrial construction company

Norbord

This project, located near Guntown, Mississippi, was constructed for Norbord, Inc. Norbord is a world recognized leader in the manufacturing of Oriented

JESCO plant manufacturing engineering

Caterpillar – Oxford

JESCO Design / Build team completed the original design and construction of the 180,000 square feet High Performance Extrusions Plant in July